When a sprint is cancelled, the Scrum team discards all the work and refines a new product backlog. a) True b) False

Autor: Avinash Upadhyay



Respuesta:

B) False The team still conducts the sprint review to review Done Product log items. If part of the work is valuable and useful, the Product owner typically accepts it. All incomplete product backlog items are re estimated and put back into pRoduct backlog .