Pregunta:

For the first sprint, the inputs are the Product backlog and projected capacity of the developers. What are the additional inputs to the subsequent sprints? Select all that apply. a) The defect list from the previous sprint b) The Sprint Plan c) The past performance of the Developers d) The latest product increment

Autor: Avinash Upadhyay



Respuesta:

C) The past performance of the Developers d) The latest product increment