Pregunta:

Sprint Backlog MUST contain at least one improvement item (identified from the Sprint Retrospective) a) True. b) False.

Autor: Avinash Upadhyay



Respuesta:

B) False. In Sprint Retrospective, the Scrum Team identifies the most helpful changes (in is way of working) to improve its effectiveness. The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint, but it is not mandatory. Correct answer is ‘b.’