Pregunta:

In the early days of a Product Development’s initial Sprint, the Product Backlog a) Only lays out the initially known and best-understood requirements. b) Is as comprehensive as required to complete the Product. c) Is not shared with the Developers until it is supplemented with other required specifications.

Autor: Avinash Upadhyay



Respuesta:

A) Only lays out the initially known and best-understood requirements. In the beginning, the Product Backlog only lays out the initially known and best-understood requirements. The Product Backlog is a living artifact that evolves and constantly changes to identify what the product needs to be appropriate, competitive, and useful. Correct answer is ‘a.’