Pregunta:
A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. The formula is VAC = BAC – EAC.
Autor: Mitch PalmerRespuesta:
Variance at completion (VAC)
0 / 5 (0 calificaciones)