Construction Contracts: (company doing the building for another company) % Profit Earned Equation
Autor: LandiniLizardRespuesta:
(Cost Incurred / Total Expected Cost) = % Complete Contract Price - Total Expected Cost = Profit Profit x % = Profit Earned