SCRUM REAL QUIZ

» Iniciar este curso
(Practica preguntas similares gratis)
Pregunta:

You are on a scrum team that is in the middle of a Sprint. Your team gets some additional team members. The Likely result is a) The team can take more stories on top of the originally forecast sprint backlog. b) The team will have to do a Sprint planning again and get buy in from the new members on the new planning. c) The Team may suffer in its productivity.

Autor: Avinash Upadhyay



Respuesta:

C) The Team may suffer in its productivity.