Pregunta:

A scrum team crafts the following Sprint Goal: "All the Sprint code should have passed 100% automated unit tests". a) Not an appropriate goal since sprint goal should be about expected Business value. b) It is incorrect since the product owner formulates the Goal not the Scrum team. c) It is well formed Sprint goal.

Autor: Avinash Upadhyay



Respuesta:

A) Not an appropriate goal since sprint goal should be about expected Business value. The Sprint Goal Reflects the intended Business functionality that will be delivered in a sprint.