Pregunta:

A scrum team has created the Sprint Backlog in the form of a task board. What is your inference? a) The team can choose to represent the Sprint Backlog in any form that makes sense to them. b) It is okay to have it in task board format, but it must be ensured that it follows all the Kanban principles c) The Scrum Master must advise the team to create a proper sprint Backlog in the form of matrix of the selected Product backlog items, related tasks, estimates, owners, and expected completion dates.

Autor: Avinash Upadhyay



Respuesta:

A) The team can choose to represent the Sprint Backlog in any form that makes sense to them. It is up to the team to choose the format of the Sprint back-log. Correct answer is "a"