Not having the Daily Scrum will a) Reduce the opportunity to create a status report. b) Reduce the speed of development work. c) Reduce the transparency of overall progress.

Autor: Avinash Upadhyay



Respuesta:

C) Reduce the transparency of overall progress. Failure to include any of the Scrum events (including the Daily Scrum) results in reduced transparency and is a lost opportunity to inspect and adapt. Correct answer is ‘c.’