Pregunta:

The Sprint Backlog is modified throughout the Sprint. As soon as a new task is identified, a) The Product Owner adds it to the Sprint Backlog and communicates it to the Scrum Team. b) The Scrum Master adds it to the Sprint Backlog and communicates it to the Scrum Team. c) The Developers add it to the Sprint Backlog and communicate it to the Scrum Team.

Autor: Avinash Upadhyay



Respuesta:

C) The Developers add it to the Sprint Backlog and communicate it to the Scrum Team. The Sprint Backlog belongs solely to the Developers. Correct answer is ‘c.’