Pregunta:

Which is the correct statement? a) The Product Backlog cannot be changed without a change request to the Product Owner. b) The Product Backlog is not updated when a Sprint is in progress. Changes to team size may cause changes in the Product Backlog. c) The Product Backlog can be updated anytime by the Product Owner. Changes in business requirements, market conditions, or technology may cause changes to the Product Backlog.

Autor: Avinash Upadhyay



Respuesta:

C) The Product Backlog can be updated anytime by the Product Owner. Changes in business requirements, market conditions, or technology may cause changes to the Product Backlog. Correct answer is ‘c.’